ROOFING:
Work almost complete, waiting for Covid infected sheet metal employee to test negative, & return to workforce- "hoping" for Monday. 1-2 days work remaining.

ELEVATOR PIT CLEANING & PAINTING:
Work complete, 2 new sump pumps installed.

SCOPING:
Work complete, waiting for report.  

B6 ELEVATOR DOOR SAFETY EDGE:
Work complete, Installed working properly.

B6 DOOR CLOSING UPGRADE:
Waiting for repair company to schedule.

RESERVE STUDY:
Work started.