Resume parking in all garages from now on, "lay up" work now complete. Balance of work is gutters & cap sheet (top sheet).
Gutters will continue and be done Thursday or Friday.
Cap sheet installation (final layer) on all 3 buildings should then take approx. 2 weeks depending upon weather.