Elevator pit maintenance projected schedule is as follows:
Monday the 11th we will complete pits 1 and 2, Tuesday the 12th we will complete pits 3 and 4, Wednesday the 13th we will complete pits 5 and 6, Thursday the 14th we will complete pits 7 and 8. We're going to use Friday the 15th as a backup date in case we run into any unforeseen issues. We will be arriving each day between 8 and 9 am.
If you need the elevator the day it is being worked on please reschedule your appointment. If you cannot, let me know "now" and I will try to reschedule vendor.
Also, consider the above schedule could vary "some" due to unforeseen issues.
Burt 617 592 3368