ROOFING: Work almost complete, waiting for Covid infected sheet metal employee to test negative, & return to workforce- "hoping" for Monday. 1-2 days work remaining.
ELEVATOR PIT CLEANING & PAINTING: Work complete, 2 new sump pumps installed.
SCOPING: Work complete, waiting for report.
B6 ELEVATOR DOOR SAFETY EDGE: Work complete, Installed working properly.
B6 DOOR CLOSING UPGRADE: Waiting for repair company to schedule.
RESERVE STUDY: Work started.